The following steps walk a user, with write access to the module and architecture, through creating a new task in LAM. This process also applies to a data set.

1. With the desired architecture loaded, ensure you are in the Gantt tab of the Content Pane.
 
2. Click on the project you want to add the task to (P-1 in the example).
 
3. In the Home tab of the Ribbon Bar, click the Task button in the Create group.
 
4. A blank Task Information window pops up. The Period of Performance dates default to those of the parent project.
 
5. In the Task tab, fill out the fields. All asterisk fields are required, and you can edit the dates as needed. Click Apply when you are finished.
 
6. In the Home tab of the Ribbon Bar, click the Show Tasks button to display tasks in the Gantt.
 
7. The new task now appears in the Gantt view.